Week of 06/22/26/Monday to 06/26/26/Friday
Crew # 1 – Morais continues constructing new concrete retaining wall West of Bashan Hill Road.
Crew # 2 – Morais continues with new drainage from River Road to Peru Town Line
Week of 06/29/26/Monday to 07/03/26/Friday
Crew # 1 – Morais continues constructing new concrete retaining wall West of Bashan Hill Road.
Note: Work hours 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
- A temporary traffic signal allowing one-way alternating traffic for approx. 400 FT has been installed and operating at the new concrete retaining wall construction site West of Bashan Hill Road.
- 07/03/Friday – No Work today observing July 4 Holiday
- Verizon Utility work is completed