Week of 08/31/Monday through 09/04/Friday
Crew # 1 – Morais Construction will continue backfilling shoulders and constructing driveway aprons from East Windsor Road to Lindsey Hill Road.
Week of 09/07/Monday through 09/11/Friday
Crew # 1 – Morais Construction will continue backfilling shoulders and constructing driveway aprons from East Windsor Road to Lindsey Hill Road.
Note: Work hours are 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
Blacktop Road Paving is completed for the season
09/07/Monday Labor Day Holiday – No Work
Lindsay Hill Road Update

Work has begun on the repairs and replacement of culverts on Lindsay Hill Road.
- The Highway Dept. has done the needed tree cutting and clearing.
- They plan on installing the sediment control next week (8/31-9/4).
- The culverts are expected to be delivered the end of next week and they’re planning starting the installation of those the week of 9/7/2026.
- Of course everything is weather dependent. We’ll continue to keep everyone posted…