Route 143/Old North Rd/Lindsay Hill Rd Construction Update 8/28/2026

Week of 08/31/Monday through 09/04/Friday

Crew # 1 – Morais Construction will continue backfilling shoulders and constructing driveway aprons from East Windsor Road to Lindsey Hill Road.

Week of 09/07/Monday through 09/11/Friday

Crew # 1 – Morais Construction will continue backfilling shoulders and constructing driveway aprons from East Windsor Road to Lindsey Hill Road.


Note: Work hours are 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.


Lindsay Hill Road Update

Work has begun on the repairs and replacement of culverts on Lindsay Hill Road.

  • The Highway Dept. has done the needed tree cutting and clearing.
  • They plan on installing the sediment control next week (8/31-9/4).
  • The culverts are expected to be delivered the end of next week and they’re planning starting the installation of those the week of 9/7/2026.
  • Of course everything is weather dependent. We’ll continue to keep everyone posted…