Week of 08/10/Monday through 08/14/Friday
Crew # 1 – Morais Construction continues reconstruction of the roadway beginning at East Windsor Road to Lindsey Hill Road, Fine Grading the roadway and placing sub drain.
Week of 08/17/Monday through 08/21/Friday
Crew # 1 – Morais Construction continues reconstruction of the roadway beginning at East Windsor Road to Lindsey Hill Road, placing Dense Graded Crushed Stone on the roadway.
Note: Work hours Monday through Friday, 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
Blacktop paving should happen in the week of Monday, 8/24/2026, working hours will be 7:00 AM to 5:00 PM, for approximately 4 days. We will keep you updated on this schedule.
Your Feedback Welcome

The project plans and specs for the Route 143 reconstruction called for temporary signals with detection for vehicles and pedestrians, as well as sequencing for pedestrians.
For the work that has been done to date, field decisions were made to eliminate the detection features and programming for pedestrians and phase the timing as per the manufacturer. So the Traffic Lights have just been on timers, vs having detection for oncoming vehicles and pedestrians.
The construction company is asking to be able to continue just using the timers for upcoming lane closures.
If you’d like to share feedback on this, please email the Selectboard at sboard@worthington-ma.us. We will be discussing this at the next Selectboard Meeting on Tuesday, August 11, 2026. (The meeting starts at 6:30 PM, and it will probably be 7:30 PM when we get to this. You can join virtually or in person)