ALERT: They will be pouring a lot of concrete this week (6/22-26) for the retaining wall under construction west of Bashan Hill Rd. That may result in considerable delays.
You may want to consider the detour from East Windsor Rd to the center of Peru. It adds approximately 7-12 minutes to the trip depending on where you’re headed, but it’s time you can count on rather than a possible long wait at the construction site.
It’s a little twisty, but signs are up and it’s well marked.
Week of 06/22/26/Monday to 06/26/26/Friday
Crew # 1 โ Morais continues constructing new concrete retaining wall West of Bashan Hill Road.
Crew # 2 โ Morais continues with new drainage from River Road to Peru Town Line
Week of 06/29/26/Monday to 07/03/26/Friday
Crew # 1 โ Morais continues constructing new concrete retaining wall West of Bashan Hill Road.
Note: Work hours 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
Lindsay Hill Road
Lindsay Hill Road remains closed due to 2 culvert washouts and is NOT available as a detour.
The Highway Department and Conservation Commission are working on a design and repair plan. Unfortunately it’s not a quick fix.
It’s a little early to estimate the time it’s going to take to installs new culverts and get the road open, but it won’t be soon. ๐ We’ll continue to keep everyone updated.
- A temporary traffic signal allowing one-way alternating traffic for approx. 400 FT has been installed and operating at the new concrete retaining wall construction site West of Bashan Hill Road.
- 07/03/Friday โ No Work today observing July 4 Holiday
- Verizon Utility work is completed