Route 143 (Old North Road)
Week of Monday, 8/25 through Friday, 8/29/25
Crew # 1 – Drilling, blasting and rock removal continues at Ledge # 2 located at West End of project. Plans are to blast Monday 8/25 and Thursday 8/28 around 9am & 12 noon.
Crew # 2 – Install drainage from Rte. 143 & East Windsor RD intersection to Liston’s.
Note: At both construction locations between the work hours of 7:00 AM to 3:30 PM one-way alternating traffic will be in place with traffic officers directing traffic. At Ledge # 2 when blasting is occurring Rte. 143 will be closed & detoured with detail officers on both sides for as short a period possible.
Route 112 (Huntington Road)
Week of Monday, 8/25 through Friday, 8/29/25
Crew # 1 repair drainage structures
No work on Monday, 9/1/2025, Labor Day Holiday
Week of Tuesday, 9/2 through Friday, 9/5/25
Possible Milling but no date set
Note: One way traffic will be in effect with traffic officers directing during work hours from 7:00 AMto 3:30 PM.