Week of 08/03/Monday through 08/07/Friday
Crew # 1 – Morais Construction continues reconstruction of the roadway beginning at East Windsor Road to Lindsey Hill Road, Fine Grading the roadway.
Week of 08/10/Monday through 08/14/Friday
Crew # 1 – Morais Construction continues reconstruction of the roadway beginning at East Windsor Road to Lindsey Hill Road, placing Dense Graded Crushed Stone on the roadway.
Note: Work hours Monday through Friday, 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.