Route 143 – Old North Road
Week of Monday, 11/03/25 through Friday, 11/07/25
Crew # 1 – Cleanup of rock at Ledge # 2 located at West End of project and a small amount of cleanup of ledge removal at Ledge # 1 near Bashan Hill Road.
Crew # 2 – Driveway & shoulder work in the road reconstruction area (between East Windsor Road & Liston’s)
Week of Monday, 11/10/25 through Friday, 11/14/25
Crew # 1 – Cleanup of rock at Ledge # 2 located at West End of project and a small amount of cleanup of ledge removal at Ledge # 1 near Bashan Hill Road.
Crew # 2 – Driveway & shoulder work in the road reconstruction area (between East Windsor Road & Liston’s)
Note: work between the work hours of 7:00 AM to 3:30 PM , one-way alternating traffic will be in place with traffic officers directing traffic.
Route 112 – Huntington Road
Week of Monday, 11/03/25 through Friday, 11/07/25
One Warner Brothers crew blacktop driveway aprons and shoulder work Monday through Friday.
Week of Monday, 11/10/25 through Friday, 11/14/25
One Warner Brothers crew blacktop driveway aprons and shoulder work Monday through Friday job should be complete this week.
Note: One way traffic with traffic officers directing traffic 7:00 AM to 3:30 PM