Weather depending, work is expected to be active till approximately December 1, 2026
Week of 11/9/Monday through 11/13/Friday
Crew # 1 – Morais Construction will be installing drainage from Retaining Wall # 2 to Peru Town Line.
Crew # 2 – Morais Construction’s subcontractor will continue constructing Retaining Wall # 2, one mile East of Worthington/Peru Town Line.
Week of 11/16/Monday through 11/20/Friday
Crew # 1 – Morais Construction will be installing drainage from Retaining Wall # 2 to Peru Town Line.
Crew # 2 – Morais Construction’s subcontractor will continue constructing Retaining Wall # 2, one mile East of Worthington/Peru Town Line.
Note: Work hours are 7:00 AM to 3:30 PM, one-way alternating traffic in place with traffic officers directing traffic for crew # 1. A temporary traffic signal is in use for crew # 2 (Retaining Wall # 2 work). 11/11/Wednesday Veteran’s Day job is active.