Construction Update for Route 143 – 6/27/2026

Week of 06/29/26/Monday to 07/03/26/Friday

Crew # 1 – Morais continues constructing new concrete retaining wall West of Bashan Hill Road

Week of 07/06/Monday to 07/10/26/Friday

Crew # 1 – Morais installs drainage culvert and repairs the road at the new concrete retaining wall West of Bashan Hill Road

Note:   Work hours 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.


Lindsay Hill Road

Lindsay Hill Road remains closed due to 2 culvert washouts and is NOT available as a detour.

The Highway Department and Conservation Commission are working on a design and repair plan. Unfortunately it’s not a quick fix.

It’s a little early to estimate the time it’s going to take to installs new culverts and get the road open, but it won’t be soon.  We’ll continue to keep everyone updated.


  • A temporary traffic signal allowing one-way alternating traffic for approx. 400 FT has been installed and operating at the new concrete retaining wall construction site West of Bashan Hill Road.
  • 07/03/Friday – No Work today observing July 4 Holiday
  • Verizon Utility work is completed