Route 143 Construction Update (Revised) 5/22/2026

Week of 05/26/Tuesday to 05/29/26/Friday

Crew # 1 – Morais begins constructing new concrete retaining wall West of Bashan Hill Road and fills in potholes.



Week of 06/01/Monday to 06/05/Friday

Crew # 1 – Morais continues constructing new concrete retaining wall West of Bashan Hill Road.



Note:   Work hours 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.