Week of 05/26/Tuesday to 05/29/26/Friday
Crew # 1 – Morais begins constructing new concrete retaining wall West of Bashan Hill Road and fills in potholes.
05/25/Monday Memorial Day Holiday – No Work
Week of 06/01/Monday to 06/05/Friday
Crew # 1 – Morais continues constructing new concrete retaining wall West of Bashan Hill Road.
Next week or the following week when required a temporary traffic signal allowing one-way alternating traffic for approx. 400 FT will be installed at the new concrete retaining wall site West of Bashan Hill Road.
Note: Work hours 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.