Week of 10/19/Monday through 10/23/Friday
Crew # 1 – Morais Construction will continue backfilling shoulders and constructing driveway aprons from East Windsor Road to Lindsey Hill Road.
Crew # 2 – Morais Construction’s subcontractor will continue constructing Retaining Wall # 2, one mile East of Worthington/Peru Town Line.
Week of 10/26/Monday through 10/30/Friday
Crew # 1 – Morais Construction will continue backfilling shoulders and constructing driveway aprons from East Windsor Road to Lindsey Hill Road.
Crew # 2 – Morais Construction’s subcontractor will continue constructing Retaining Wall # 2, one mile East of Worthington/Peru Town Line.
Note: Work hours are 7:00 AM to 3:30 PM, one-way alternating traffic in place with traffic officers directing traffic for shoulder work and a temporary traffic signal is in use at Retaining Wall # 2.