Week of 07/13/Monday through 07/17/Friday
Crew # 1 – Morais Construction repairs road and installs drainage culvert at the new concrete retaining wall West of Bashan Hill Road on 7/13/Monday & 7/14/Tuesday. Beginning on 07/14/Wednesday they will begin road reconstruction starting at East Windsor Road.
Week of 07/20/Monday through 07/24/Friday
Crew # 1 – Morais Construction continues reconstruction of the roadway beginning at East Windsor Road to Lindsey Hill Road, removing the existing blacktop on the roadway.
Note: Work hours Monday through Friday, 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
The temporary traffic signal has been removed at the retaining wall work West of Bashan Hill Road and two way traffic has been restored