Week of 06/15/26/Monday to 06/19/26/Friday
Crew # 1 – Morais continues constructing new concrete retaining wall West of Bashan Hill Road.
Crew # 2 – Morais continues with new drainage from River Road to Peru Town Line
Week of 06/22/26/Monday to 06/26/26/Friday
Crew # 1 – Morais continues constructing new concrete retaining wall West of Bashan Hill Road.
Crew # 2 – Morais continues with new drainage from River Road to Peru Town Line
Note: Work hours 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
A temporary traffic signal allowing one-way alternating traffic for approx. 400 FT has been installed and working at the new concrete retaining wall construction site West of Bashan Hill Road.
- 06/19/Friday – Juneteenth Holiday crews are working.
- Verizon Utility work is completed