Route 143 (Old North Rd)
Week of Monday, 10/27 through Friday, 10/31/25
Crew # 1 – Continuerock removal at Ledge # 2 located at West End of project and small amount of cleanup ledge removal at Ledge # 1 near Bashan Hill Road.
Crew # 2 – Blacktop Pave Road Reconstruction (from Rte. 143 & East Windsor RD intersection to Liston’s) Monday, Tuesday & Wednesday. Driveways and shoulder work in this area Thursday & Friday.
Week of Monday, 11/03 through Friday, 11/07/25
Crew # 1 – Continue rock removal at Ledge # 2 located at West End of project and small amount of cleanup ledge removal at Ledge # 1 near Bashan Hill Road.
Crew # 2 – Driveway & shoulder work in the road reconstruction area.
Note: Non paving construction locations work between the work hours of 7:00 AM to 3:30 PM and Blacktop paving work hours are 6:30 AM to 5:00 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
Week of Monday, 10/27 through Friday, 10/31/25
One Warner Brothers crew blacktop driveway aprons and shoulder work Monday through Friday.
One Warner Crew Loam & seed Monday through Friday.
Week of Monday, 11/03 through Friday, 11/07/25
One Warner Brothers crew blacktop driveway aprons and shoulder work Monday through Friday.
Note: One way traffic with traffic officers directing traffic 7:00 AM to 3:30 PM