Route 143 (Old North Road)
Week of Monday, 9/8/25 through Friday 9/12/25
Crew # 1 – Continue drilling, blasting and rock removal at Ledge # 2 located at West End of project between River Rd and the Peru line. Blasting is planned for Monday 9/8 and Wednesday 9/10 and should be wrapped up with Phase 2 until excavation is complete. They will most likely conduct clean up blasting the following week on Phase 1, but I will update everyone next week on that.
Crew # 2 – Continue Road Reconstruction (mill off blacktop and then install gravel base) from Rte. 143 & East Windsor RD intersection to Liston’s. (This will take the month of September followed by blacktop paving of this area in October)
Note:
At both construction locations between the work hours of 7:00 AM to 3:30 PM one-way alternating traffic will be in place with traffic officers directing traffic.
At Ledge # 2 when blasting is occurring Rte. 143 will be closed & detoured if needed with detail officers on both sides for as short a period possible.
Route 112 (Huntington Road)

Week of Monday, 9/8/25 through Friday 9/12/25
Monday & Tuesday complete Roadway milling. Wednesday through Friday one Warner Brothers crew will be doing miscellaneous work to prepare for paving.
Week of Monday, 9/15/25 through Friday 9/20/25
One Warner Brothers crew will be doing miscellaneous work to prepare for paving.
Note:
One way traffic will be in effect for milling with traffic officers directing during work hours from 7:00 AM to 3:30 PM.
