Week of 09/07/Monday through 09/11/Friday
Crew # 1 – Morais Construction will continue backfilling shoulders and constructing driveway aprons from East Windsor Road to Lindsey Hill Road.
Crew # 2 – Guardrail subcontractor will complete guardrail work from East Windsor Road to Lindsey Hill Road.
Week of 09/14/Monday through 09/18/Friday
Crew # 1 – Morais Construction will continue backfilling shoulders and constructing driveway aprons from East Windsor Road to Lindsey Hill Road.
Note: Work hours are 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
Blacktop Road Paving is completed for the season
09/07/Monday Labor Day Holiday – No Work