Week of 07/06/Monday to 07/10/26/Friday
Crew # 1 – Morais installs drainage culvert and repair the road at the new concrete retaining wall West of Bashan Hill Road.
Week of 07/13/Monday to 07/17/26/Friday
Crew # 1 – Morais begins excavating old blacktop road for road reconstruction from East Windsor Road to Bashan Hill Road.
Note: Work hours 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.
A temporary traffic signal allowing one-way alternating traffic for approx. 400 FT has been installed and operating at the new concrete retaining wall construction site West of Bashan Hill Road.
Lindsay Hill Road Update

The Conservation is working on a plan for the wetlands around the washed out culverts and the Highway Department is expecting delivery of a new Excavator this month which will facilitate the culvert replacements. Both should hopefully allow for repairs and reopening around the end of summer. Nothing is firm yet, but we’ll keep you posted.