Road Construction Update

This project is largely complete!

Please note: There is fresh sand around the new sidewalks from Town Hall to the School. Please do not pull onto or across the sand as you and your car will just make big ruts. The area is marked with wooden markers. Please also avoid walking on the sand, as it is very soft.


Week of 11/17/25/Monday through 11/21/25/Friday

Crew # 1 – Cleanup of rock at Ledge # 2 located at West End of project and at Ledge # 1 near Bashan Hill Road.

Crew # 2 – Driveway & shoulder work in the road reconstruction area (between East Windsor Road & Liston’s)

Crew # 3 – Install new guardrail in the road reconstruction area (between East Windsor Road & Liston’s)

Week of 11/10/25/Monday through 11/14/25/Friday

Same as previous week

Note: work between the hours of 7:00 AM to 3:30 PM, one-way alternating traffic will be in place with traffic officers directing traffic.