Route 143 (Old North Road)
Week of Monday, 9/29/25 through Friday, 10/3/25
Crew # 1 – Continue rock removal at Ledge # 2 located at West End of project and a small amount of cleanup and removal at Ledge # 1 near Bashan Hill Road.
Crew # 2 – Continue Road Reconstruction (install gravel base, then Fine Grade from Rte. 143 & East Windsor RD intersection to Liston’s).
Week of Monday, 10/5/25 through Friday, 10/10/25
Crew # 1 – Continue rock removal at Ledge # 2 located at West End of project and a small amount of cleanup and removal at Ledge # 1 near Bashan Hill Road.
Crew # 2 – Continue Road Reconstruction (install Dense Graded Crushed Stone from Rte. 143 & East Windsor RD intersection to Liston’s). Blacktop paving to follow.
The current estimate to begin paving is Monday, October 13.
Note: At both construction locations between the work hours of 7:00 AM to 3:30 PM one-way alternating traffic will be in place with traffic officers directing traffic.
Route 112 (Huntington Road)
Week of Monday, 9/29/25 through Friday, 10/3/25
One Warner Brothers crew will be doing miscellaneous work to prepare for paving Monday, Tuesday, Wednesday.
One Warner Brothers paving crew will begin blacktop road paving beginning at Huntington town line Thursday & Friday.
Week of Monday, 10/5/25 through Friday, 10/10/25
One Warner Brothers paving crew will complete blacktop road paving beginning at Huntington town line Monday through Friday.
Note: One way traffic with traffic officers directing traffic during paving hours from 6:30 AMto 5:00 PM.