Worthington, Rte. 143
Two Week Look Ahead
Week of Monday – 7/14/2025
through Friday – 7/18/2025
Crew # 1 – Begin Blasting and rock removal Ledge # 2
Crew # 2 – Backfill Retaining Wall # 3 and continue construction of Retaining Wall # 6
Week of Monday – 7/21/2025
through – Friday – 7/25/2025
Same as above
Worthington, Rte. 112
Two Week Look Ahead
Week of Monday – 7/14/2025
through Friday – 7/18/2025

Crew # 1 – Continue removing & replacing existing guardrail with new
Crew # 2 – Repairing blacktop waterways on the shoulders of the road
Week of Monday – 7/21/2025
through – Friday – 7/25/2025
Same as above
When will 143 be open again to traffic?
Route 143 is open through this weekend and will close on Monday 7/21 for 2-3 weeks between East Windsor Rd & Bashan Hill Rd.
https://worthington-ma.us/2025/07/route-143-road-closure/
When will 143 be open again to traffic?